Federal Prompt Payment for Construction Work Act (S.C. 2019, c. 29, s. 387)

Act current to 2022-07-25

Payments Between Parties (continued)

Holdback

The following provision is not in force.

Marginal note:Payment subject to holdback

  • The following provision is not in force.

     (1) Any payment for construction work made to a party under subsection 9(2), 10(1) or 11(1) may be subject to a holdback provided for by the contract entered into between that party and the party that is to pay them.

  • The following provision is not in force.

    Marginal note:Limit

    (2) However, the amount of a holdback made under the contract cannot exceed what that amount would be if the holdback was made under the construction law of the province in which the construction project is located.

  • The following provision is not in force.

    Marginal note:Payment of holdback

    (3) The amount of the holdback must be paid by no later than the day on which that payment would be made under the construction law of the province in which the construction project is located.

Non-payment

The following provision is not in force.

Marginal note:Notice of non-payment

 A notice of non-payment must include the following:

  • The following provision is not in force.

    (a) a description of the construction work covered by the notice of non-payment;

  • The following provision is not in force.

    (b) the amount that will not be paid;

  • The following provision is not in force.

    (c) the reasons for the non-payment, including whether the party that must pay does not have the necessary funds to do so as a result of also receiving a notice of non-payment that covers the construction work referred to in paragraph (a); and

  • The following provision is not in force.

    (d) any other information prescribed by regulation.

The following provision is not in force.

Marginal note:Interest on unpaid amounts

  • The following provision is not in force.

     (1) Interest must be paid and begins to accrue on the following unpaid amounts from the expiry of the time limit for payment provided under this Act or, when applicable, the shorter time limit set out in the contract between the parties:

    • The following provision is not in force.

      (a) any amount that is not covered by a notice of non-payment;

    • The following provision is not in force.

      (b) any amount that is covered by a notice of non-payment, if the only reason for non-payment of that amount is that the party that must pay does not have the necessary funds to do so as a result of also receiving a notice of non-payment that covers the construction work that must be paid for; and

    • The following provision is not in force.

      (c) any amount that is covered by a notice of non-payment, if there is a reason for non-payment of that amount other than the reason referred to in paragraph (b), but only for the portion of that amount that an adjudicator orders to be paid.

  • The following provision is not in force.

    Marginal note:Applicable interest rate

    (2) The interest rate applicable to the amounts referred to in subsection (1) is the rate prescribed by regulation or, if the contract between the parties sets out an interest rate, the greater of the rate prescribed by regulation and the rate set out in the contract.

Dispute Resolution

The following provision is not in force.

Marginal note:Designation

 The Minister may, in accordance with any criteria prescribed by regulations, designate the Adjudicator Authority.

The following provision is not in force.

Marginal note:Adjudication

  • The following provision is not in force.

     (1) If a contractor or subcontractor has not been fully paid for its construction work within the time limit for payment provided under this Act or, when applicable, the shorter time limit set out in its contract, that contractor or subcontractor may obtain from an adjudicator a determination respecting any dispute over the non-payment by the party that is to pay it under the contract.

  • The following provision is not in force.

    Marginal note:Notice to other party

    (2) A contractor or subcontractor that seeks to have the dispute referred to in subsection (1) determined by an adjudicator must provide the party that is to pay it under the contract with a notice of adjudication no later than the 21st day after the later of the following:

    • The following provision is not in force.

      (a) the day on which the contractor receives a certificate of completion with respect to the construction project from Her Majesty or a service provider; and

    • The following provision is not in force.

      (b) if any of its construction work is covered by the last proper invoice submitted with respect to the construction project, the expiry of the time limit provided under this Act for payment for that work.

  • The following provision is not in force.

    Marginal note:Notice of adjudication

    (3) A notice of adjudication must include the following:

    • The following provision is not in force.

      (a) the names of the parties to the dispute;

    • The following provision is not in force.

      (b) a brief description of the dispute, including details of how and when it arose;

    • The following provision is not in force.

      (c) the amount requested to be paid;

    • The following provision is not in force.

      (d) the name of a proposed adjudicator; and

    • The following provision is not in force.

      (e) any other information prescribed by regulation.

  • The following provision is not in force.

    Marginal note:Proposed adjudicator

    (4) For the purposes of paragraph (3)(d), the name must be selected from a list of adjudicators established by the Adjudicator Authority and that selection cannot be restricted by contract.

  • The following provision is not in force.

    Marginal note:Right to information — certificate of completion

    (5) On request, a contractor must inform any subcontractor in the subcontracting chain of the date on which the contractor received a certificate of completion with respect to the construction project from Her Majesty or the service provider.

The following provision is not in force.

Marginal note:Joint appointment

  • The following provision is not in force.

     (1) The parties to a dispute must jointly appoint an adjudicator to determine the dispute.

  • The following provision is not in force.

    Marginal note:Request for appointment

    (2) If the parties are unable to jointly appoint an adjudicator, either party may request that the Adjudicator Authority appoint an adjudicator for them.

  • The following provision is not in force.

    Marginal note:Appointment

    (3) On request, the Adjudicator Authority must appoint an adjudicator from a list of adjudicators it has established.

  • The following provision is not in force.

    Marginal note:Consent

    (4) The appointment of an adjudicator is subject to that adjudicator’s consent.

The following provision is not in force.

Marginal note:Determination

  • The following provision is not in force.

     (1) An adjudicator must, except in the cases provided for in the regulations, determine the dispute.

  • The following provision is not in force.

    Marginal note:Determination binding

    (2) The adjudicator’s determination is binding on the parties to the dispute unless they come to a written agreement or the determination is set aside by a court order or arbitral award.

  • The following provision is not in force.

    Marginal note:Authority of court or arbitrator

    (3) Nothing in this Act restricts the authority of a court or of an arbitrator to consider the merits of a matter determined by an adjudicator.

The following provision is not in force.

Marginal note:Compliance with determination

  • The following provision is not in force.

     (1) If a party that is to pay for construction work under its contract is ordered by the adjudicator to make a payment, the party must make the payment no later than the 10th day after the day on which it received the adjudicator’s determination, or within any other time limit set out in the determination.

  • The following provision is not in force.

    Marginal note:Filing of decision

    (2) If the party that is ordered to make the payment fails to do so within the applicable time limit, the party that is to be paid may

    • The following provision is not in force.

      (a) suspend further construction work without this constituting a breach of the terms of its contract; and

    • The following provision is not in force.

      (b) file in the Federal Court or a superior court of a province, as the case may be, a certified copy of the adjudicator’s determination within two years after the day on which that determination was received.

  • The following provision is not in force.

    Marginal note:Effect of filing

    (3) On the certified copy being filed, the determination becomes and may be enforced as an order of the Federal Court or superior court of a province, as the case may be.

The following provision is not in force.

Marginal note:Costs, fees and expenses

  • The following provision is not in force.

     (1) Subject to subsection (2), each party to the adjudication must pay its own costs and an equal portion of the adjudicator’s fees and expenses.

  • The following provision is not in force.

    Marginal note:Exception

    (2) If the adjudicator is of the opinion that a party has acted in an abusive, scandalous or vexatious manner or in bad faith, the adjudicator may order that party to pay some or all of the other party’s costs or some or all of the other party’s portion of the adjudicator’s fees and expenses.

The following provision is not in force.

Marginal note:No summons

 The adjudicator is not to be required to produce or give evidence in respect of any matter that comes to their knowledge as a result of exercising their powers or performing their duties or functions under this Act.

General Provisions

The following provision is not in force.

Marginal note:Regulations — Minister

 The Minister may make regulations prescribing

  • The following provision is not in force.

    (a) the information referred to in section 8 and the form and manner in which it is to be submitted;

  • The following provision is not in force.

    (b) the form and content of a proper invoice and the manner in which it is to be submitted;

  • The following provision is not in force.

    (c) the form and any additional content of a notice of non-payment and the manner in which it is to be submitted;

  • The following provision is not in force.

    (d) the powers, duties and functions of the Adjudicator Authority;

  • The following provision is not in force.

    (e) the eligibility and qualifications of individuals who may be designated as adjudicators;

  • The following provision is not in force.

    (f) the powers, duties and functions of adjudicators;

  • The following provision is not in force.

    (g) the maximum fees for the services of an adjudicator;

  • The following provision is not in force.

    (h) the form and any additional content of a notice of adjudication and the manner in which it is to be submitted; and

  • The following provision is not in force.

    (i) the procedure and time limits governing the adjudication.

The following provision is not in force.

Marginal note:Regulations — Governor in Council

 The Governor in Council may make regulations generally for carrying out the purposes and provisions of this Act, including regulations prescribing

  • The following provision is not in force.

    (a) criteria for the purpose of subsection 6(1); and

  • The following provision is not in force.

    (b) in respect of any province, any days that are to be excluded from the computation of time for the purposes of the time limits referred to in sections 9 to 11.

The following provision is not in force.

Marginal note:Section 126 of Criminal Code

 Section 126 of the Criminal Code does not apply to or in respect of any contravention or alleged contravention of any provision of this Act or its regulations.

Transitional Provision

The following provision is not in force.

Marginal note:Non-application for one year

 For one year after the day on which this Act comes into force, this Act does not apply in respect of the following contracts to perform construction work:

  • The following provision is not in force.

    (a) a contract entered into by a contractor, before the day on which this Act comes into force, with Her Majesty or a service provider; and

  • The following provision is not in force.

    (b) a contract entered into by a subcontractor, before the day on which this Act comes into force or within one year after that day, with a contractor referred to in paragraph (a) or with any other subcontractor.

 
Date modified: