Canadian Energy Regulator Pipeline Damage Prevention Regulations – Authorizations
Version of section 11 from 2020-03-16 to 2024-10-30:
Marginal note:Authorization — activity required for maintenance of facility
11 For the purposes of subsection 335(1) of the Act, any maintenance of an existing facility — in an area other than an offshore area — that causes a ground disturbance within the prescribed area is authorized if the person engaged in the maintenance complies with paragraphs 10(1)(b) and (c) and the measures set out in paragraphs 10(3)(c) to (h).
- SOR/2019-349, s. 8
- Date modified: