Government of Canada / Gouvernement du Canada
Symbol of the Government of Canada

Search

Canadian Energy Regulator Processing Plant Regulations

Version of section 7 from 2020-03-16 to 2024-06-11:


 The Commission may order a company to submit to the Commission within a specified period a design, specification, program, manual, procedure, measure, plan or document if

  • (a) the company makes an application to the Commission under Part 3 or 6 of the Act; or

  • (b) the Commission receives any information that the design, construction, operation or abandonment of the company’s processing plant, or a part of it, is or may cause

    • (i) a detriment to property or to the environment; or

    • (ii) a hazard to the safety of persons.

  • SOR/2020-50, s. 33
  • SOR/2020-50, s. 35

Date modified: